Project Accountability
LIVE WORK REGISTER · 8 ROOMS / AREAS

Pending item tracker

A room-by-room execution board sourced directly from the master sheet. Unchecked tasks struck off in the sheet are handled independently and excluded from the interior team’s pending count.

Connecting to sheet…Automatic 30-second refresh
61 pending33 completed by interior team · 0 completed independently · 7 out of interior scope · 101 tracked
Out of Interior Scope

Not assigned to the interior team and being handled independently.

Completed Independently

Out-of-scope work completed separately by Rohit and Sharoon.

ROOM / AREA

Master Bedroom (MBR)

15pending from interior team
02

Complete the grooves for profile lights and the cut-outs for socket points in the dressing unit, including the open unit and below the dressing unit.

15 Aug 2026Latest

Grooves for the profile lights and cut-outs for the socket points are pending in the dressing unit, including the open unit and below the dressing unit.

Pending
03

Complete the deco paint and installation of the dressing unit, including the push-to-open mechanism for the shutters.

15 Aug 2026Latest

Deco paint and installation of the dressing unit, including the push-to-open mechanism for the shutters, are pending.

Pending
05

Confirm the headboard fabric.

21 Jul 2026

Master-bedroom headboard fabric selection scheduled for Thursday first half. The Interior team will bring paint sample 260508.

26 Jul 2026

Headboard fabric was selected last Thursday. Installation is still pending.

28 Jul 2026

Quotation will be shared.

15 Aug 2026Latest

Fabric has been selected and the quotation has been shared. reviewed and approved the quotation. The amount was not reduced after negotiation, and confirmed to proceed. Payment details are awaited so payment can be made. No installation work has started yet; this item remains pending.

Pending
06
🚨Red Priority · Needs priority action

Complete and coordinate the bed hydraulic lift, headboard fixing, damaged laminate repairs, side-drawer alignment, electrical-board cut-outs, and access-point shelf clearance.

Coordinate the hydraulic lift and headboard; prevent interference or damage and complete all related finishing.

15 Aug 2026Latest

Pending. Ensure the headboard fixing does not touch or interfere with the bed hydraulic lift and does not cause any damage or operational issues. Fix the damaged laminates in the bed unit. Align the side-drawer unit properly. Provide and correctly align the electrical-board cut-outs in the headboard above the side drawer and below the side drawer. Also account for the planned small 6×6-inch glass shelf below the drawer for the Wi-Fi access point, so the headboard installation does not obstruct or interfere with it.

Red Priority
08

Provide a small shelf below the bedside drawer for keeping the Wi-Fi access point.

21 Jul 2026

Provide a 4×4-inch glass shelf in the Wi-Fi router corner, above the skirting line. Glass preferred over ply/laminate.

26 Jul 2026

Still pending. Same update as previous.

28 Jul 2026

Additional work will be carried out after fabric installation.

15 Aug 2026Latest

This will be completed after the headboard fabric is installed. Agreed shelf size can be either 4×4 inches or 6×6 inches. The glass edges must be rounded/curved and must not have any sharp edges.

Pending
10

Provide ventilation in the dry-clothes hanging closet.

21 Jul 2026

Cloth-hanging and ventilation marking still pending. Interior team committed to complete within 2 days.

26 Jul 2026

Dryer/hanger-clothes ventilation is still pending and not yet completed.

28 Jul 2026

Will be delivered to the site.

15 Aug 2026Latest

CNC vent cutting has been completed on the lower portion of the dry-clothes hanging unit, but the CNC vent cutting on the top is still missing. The push-to-open mechanism is also missing for this unit. Both the top ventilation cut-out and the push-to-open mechanism remain pending.

Pending
13

Install two pending hanger rods inside the master-bedroom wardrobe.

26 Jul 2026

Hanger rods are pending and must be installed inside the master-bedroom wardrobe.

28 Jul 2026

Will be delivered to the site.

15 Aug 2026Latest

Installation of two hanger rods inside the master-bedroom wardrobe is still pending.

Pending
14

Install all pending knobs and handles in the master bedroom, including the wardrobe and master bathroom units.

15 Aug 2026Latest

Install all pending knobs and handles in the master bedroom. This includes the master-bedroom wardrobe handles/knobs, the missing indoor handle for the master bathroom door, and two missing knobs inside the master bathroom — one for the unit to the left of the mirror and one for the unit below it. These knobs and handles have not yet been installed and remain pending.

Pending
15
⚠️Amber Warning · Needs priority action

Install the drawer knob inside the master-bedroom wardrobe with sufficient clearance so it never touches the Aristo sliding door.

Wardrobe drawer knob must have zero contact with the Aristo sliding door.

15 Aug 2026Latest

While installing the knob on the drawer inside the master-bedroom wardrobe, ensure the knob is positioned and aligned with sufficient clearance from the Aristo sliding wardrobe door. The knob must not touch, rub against, scrape, interfere with, or make contact with the Aristo sliding door at any point while opening, closing, or sliding — even marginally. Verify the clearance after installation and adjust the knob/drawer position if required so there is zero contact with the Aristo door. This item remains pending.

Amber Warning
16

Install the pending drawer locks and fingerprint lock inside the master-bedroom wardrobe after painting is completed.

15 Aug 2026Latest

Installation of the drawer locks inside the master-bedroom wardrobe is pending. The fingerprint lock installation inside the wardrobe is also pending. Both the drawer locks and fingerprint lock are to be installed after the painting is completed. This item remains pending.

Pending
17

Install the missing shelves in the master bathroom units and confirm shelf heights before installation.

15 Aug 2026Latest

Shelves are missing in multiple master-bathroom units. Install the missing shelves in the unit to the left of the mirror and the unit below it; install the missing shelf in the bi-fold-door unit; and provide one single shelf in the unit next to the commode. Confirm the shelf heights with and Sharoon before installation. This item remains pending.

Pending
18

Install a removable dummy panel on the left side of the mirror in the master bathroom to cover the visible gap and wires.

15 Aug 2026Latest

A large gap is visible on the left side of the mirror in the master bathroom, and electrical wires are exposed. Provide and install a removable dummy panel next to the mirror on the left side to neatly conceal the gap and wires while retaining access when required. This item remains pending.

Pending
19

Cover and finish all visible screws and joints seamlessly, especially across the master-bedroom wardrobe unit.

15 Aug 2026Latest

All visible screws, screw heads, joints, and connection points must be covered and finished seamlessly, especially on the master-bedroom wardrobe unit. No exposed screws or visibly unfinished joints should remain. This item is pending.

Pending
20

Install the dummy panel above the master-bedroom wardrobe after the profile lights inside the wardrobe are installed.

15 Aug 2026Latest

The dummy panel above the master-bedroom wardrobe must be installed only after the profile lights inside the wardrobe are installed and completed. This item remains pending.

Pending
21

Fix the alignment of the master-bedroom bathroom geyser and softener-unit shutters so they close properly.

15 Aug 2026Latest

The shutters for the master-bedroom bathroom geyser and softener unit are not closing properly because the alignment is incorrect. Correct the alignment so both shutters close properly and operate smoothly. This item remains pending.

Pending
ROOM / AREA

Dining Area

5pending from interior team
22
🚨Red Priority · Needs priority action

Fix the gaming-room hidden door installation on priority.

₹1 lakh hidden-door hinge system requires complete correction from both outside and inside.

15 Aug 2026Latest

Major pending item. The gaming-room hidden door installation requires immediate rectification. The hidden-door hinge system, valued at approximately ₹1 lakh, has not been installed to the expected quality. The hinges are touching the laminate behind the door, the internal dummy panel is coming out, the door is not operating properly, the alignment is significantly off, and the door does not achieve the intended hidden-door finish. Fix the hinge clearance, secure the dummy panel, correct the complete door alignment and finishing, and ensure the door opens and closes smoothly without touching or damaging the laminate. The installation and finishing must also be completed properly from the inside of the gaming room, including the inside grooves, alignment, concealed finishing, and all visible gaps. This must be taken up on priority and completed properly. The separate gaming-room door item previously listed as point 48 was a duplicate and has been consolidated into this point 21.

Red Priority
23

First provide wallpaper options for selection and approval, and then install the finalized wallpaper in the dining area.

21 Jul 2026

Canvas wallpaper sourced. Selection scheduled Thursday; expected dispatch approximately 10 days after final selection, followed by installation.

26 Jul 2026

Still pending. Wallpaper options have not yet been provided. No selection is finalized and installation is pending.

28 Jul 2026

Options will be shared today. Installation will be done after deep cleaning.

15 Aug 2026Latest

Wallpaper options were provided by the interior team, but none of the options were liked/finalized. and Sharoon are now looking for better wallpaper options and will share shortlisted options with the interior team shortly. Wallpaper is still not finalized as of today and installation remains pending.

Pending
24
⚠️Amber Warning · Needs priority action

Align the skirting of the wallpaper unit and the adjacent storage unit so both are at the same level with a seamless hidden finish.

Wallpaper unit and hidden-storage skirting must remain level, gap-free and seamless top-to-bottom.

15 Aug 2026Latest

The skirting of the wallpaper unit and the adjacent storage unit must be aligned at exactly the same level. There should be no niche, recess, step, gap, or uneven transition created between the two units. The skirting should run continuously and seamlessly across both units. The adjacent storage-unit door must retain a proper hidden-door appearance from top to bottom, with the skirting and overall finishing aligned so the storage unit looks fully concealed and integrated with the wallpaper unit. This item remains pending.

Amber Warning
25

Install the missing door for the storage unit next to the wallpaper unit.

15 Aug 2026Latest

The storage-unit door next to the wallpaper unit has not yet been installed. Install and complete the missing door. This item remains pending.

Pending
27

Install drawer locks / RFID locks for all drawers in the dining area, especially the drawers below the glass partition.

15 Aug 2026Latest

Install suitable drawer locks / RFID locks for all drawers in the dining area, with particular attention to the drawers below the glass partition. Installation remains pending.

Pending
ROOM / AREA

Bathrooms

2pending from interior team
33
⚠️Amber Warning · Needs priority action

Lower the common-bathroom mirror above the small sink by approximately 5–6 inches.

Lower the common-bathroom mirror by approximately 5–6 inches and reinstall it safely with correct alignment.

15 Aug 2026Latest

The mirror installed above the small sink in the common bathroom is currently positioned too high and does not look proportionate or comfortable at the present height. Carefully remove and reinstall the mirror approximately 5–6 inches lower than its current position, while maintaining proper alignment with the sink/vanity and surrounding finishes. Ensure the mirror is securely fixed, level, visually balanced, and installed without damaging the wall, tiles, electrical points, or nearby fixtures. This remains pending.

Amber Warning
34
🚨Red Priority · Needs priority action

Repair and finish the damaged wall outside the common bathroom inside the duct, and properly align the AC pipes with the drain pipe.

Repair and finish the open duct wall; align and securely fix the AC pipes beside the drain pipe.

15 Aug 2026Latest

The wall outside the common bathroom, inside the duct area, is damaged and currently left open/unfinished. Repair, plaster, and finish the damaged wall properly. The AC pipes in this area are also not aligned or secured correctly and must be neatly aligned with the drain pipe, properly supported/fixed, and finished so the area is not left exposed or untidy. Ensure the AC piping and drain-pipe routing are orderly, secure, and do not interfere with access or drainage. This item remains pending.

Red Priority
ROOM / AREA

Guest Bedroom

6pending from interior team
39

Confirm the headboard fabric matching the blue laminate.

21 Jul 2026

Guest-bedroom fabric selection scheduled Thursday first half, to match the blue laminate.

26 Jul 2026

Fabric was selected on Thursday as scheduled. Installation is still pending.

28 Jul 2026

Quotation will be shared.

15 Aug 2026Latest

Guest-bedroom headboard fabric has been selected and the quotation has been approved. After negotiation, the amount was not reduced, but confirmed to proceed. Waiting for the payment details from the interior team so payment can be made. No installation work has started yet; this item remains pending.

Pending
40

Install locks for the drawers located inside the wardrobe.

21 Jul 2026

Lock plan confirmed: last corner unit gets fingerprint lock; two other units get RFID locks. Drawer-lock feasibility to be checked on-site because not all drawers can accommodate locks.

26 Jul 2026

Locks are still pending and have not yet been installed.

28 Jul 2026

Will be completed by Saturday.

15 Aug 2026Latest

One RFID drawer lock has been installed inside the guest-bedroom wardrobe for testing. The installed lock has a minor alignment issue that needs correction. All remaining drawer locks are still pending and should be installed after painting is completed. Locks are also required for the drawers below the bed, in addition to the remaining drawers inside the wardrobe. One wardrobe-drawer lock is installed; all others remain pending.

Pending
41
⚠️Amber Warning · Needs priority action

Fix the pressure-pump area and finish the wall behind it.

Complete proper cement finishing on the pressure-pump wall inside the guest-bedroom duct area.

Earlier update

Pressure-pump area, wall finish, and nearby wall damage remain pending for correction.

28 Jul 2026

Will be updated. Additional installation charges will be shared.

15 Aug 2026Latest

The pressure pump has been fixed. However, the wall behind it, at the duct outside, has not been properly finished with cement and remains incomplete. The task is still pending until the wall finish is completed properly.

Amber Warning
43

Install the pending hanger rods inside the guest-bedroom wardrobe.

26 Jul 2026

Hanger rods are pending and must be installed inside the guest-bedroom wardrobe.

28 Jul 2026

Will be delivered to the site.

15 Aug 2026Latest

Four hanger rods are pending in the guest-bedroom wardrobe. Three are required on the left side: two sari hanger rods for the upper and lower sari sections, and one hanger rod for suits. One additional hanger rod is required on the right-side wardrobe. All four hanger rods remain pending for installation.

Pending
44

Install the missing tower bolt and inside handle for the guest-bedroom door.

15 Aug 2026Latest

Tower bolt and inside handle for the guest-bedroom door are missing and remain pending. Install both from inside the guest bedroom so the door can be properly secured and operated from the room side.

Pending
45
🚨Red Priority · Needs priority action

HIGH PRIORITY — Fix the guest-bedroom hidden door completely, including gaps, alignment, grooves, hinge-side finishing, and the pending adjacent storage door installation.

Rejected completion: correct gaps, alignment, grooves, light leakage, MDF and the adjacent storage door.

26 Jul 2026

The Ozone auto-close hinge has been installed on the guest-bedroom door, but the wood is bulging near the hinges. The bulged wood must be properly rectified so the door surface is even and finished correctly. The routed grooves inside the door must be aligned and finished properly. The auto-close hinge must also be adjusted so the guest-bedroom door closes smoothly and works perfectly. This remains pending.

28 Jul 2026

Completed.

15 Aug 2026Latest

The 28 Jul 2026 completion update from the interior team is not accepted based on the current site condition. The guest-bedroom hidden door still has multiple issues and remains pending. There are visible gaps around and above the door; MDF must be added above the door to reduce the gap, as discussed on site. The door alignment is incorrect and the hidden-door finish is not achieved. The groove on the left side is missing, and the grooves around the opening/closing edges are not properly made or aligned. Light is passing through near the hinge side and this must be fully closed so no light is visible through the gaps. The overall finishing and alignment must be corrected so the door looks properly hidden and operates smoothly. In addition, the storage door next to the guest-bedroom door has still not been installed and remains pending. This is a high-priority item and is not considered completed.

Red Priority
ROOM / AREA

Gaming Room

10pending from interior team
46
⚠️Amber Warning · Needs priority action

Complete the lift-up drawer unit in the gaming room.

Install the gaming-room lift-up drawer; its material and mechanism are already ready on site.

21 Jul 2026

Work not yet started. Team must notify before installation because his presence is required for gap/frame fitting. Retain the maintenance access door behind the unit.

26 Jul 2026

Work has not yet started and remains pending. Same update as previous.

28 Jul 2026

Will be cleared by Saturday.

15 Aug 2026Latest

The lift-up drawer unit material is available on site and the lift mechanism is ready. Installation by the interior team is still pending and has not yet been completed as of today.

Amber Warning
47
⚠️Amber Warning · Needs priority action

Provide a vertical support partition in the gaming-room seating area to prevent bending and contact with the doors near the window.

Complete the required structural support for the gaming-room seating.

15 Aug 2026Latest

The gaming-room seating area is bending in the middle and is touching the doors near the window. Provide a proper vertical support partition/support in between the seating area so it remains structurally supported and does not bend or interfere with the nearby doors. This support partition is pending.

Amber Warning
48
⚠️Amber Warning · Needs priority action

Install two missing shelves with backside cut-outs inside the network / smart-home hub unit.

Install the missing shelves inside the gaming-room network hub.

15 Aug 2026Latest

Two shelves inside the network / smart-home hub unit are missing. Install two shelves, each with the required backside cut-out as discussed earlier, so cables and connections can pass through properly. This remains pending.

Amber Warning
49
⚠️Amber Warning · Needs priority action

Install the missing wire-manager closer/cover inside the network / smart-home hub unit.

Complete the pending wire-manager cover in the gaming-room network hub.

15 Aug 2026Latest

The wire-manager cut-out inside the network / smart-home hub unit has been left open because the wire-manager closer/cover is missing. Install the required wire-manager closer/cover and finish the opening properly. This remains pending.

Amber Warning
50
⚠️Amber Warning · Needs priority action

Complete the missing CNC cut-outs on the network / smart-home hub door for the cooling fan and display.

Complete the pending CNC fan and display cut-outs.

15 Aug 2026Latest

CNC cutting / cut-outs for the cooling fan and display on the network / smart-home hub door in the gaming room are still pending. The template has been kept ready for approximately six months, but the door cut-outs have not yet been completed. Complete both cut-outs properly as per the provided template.

Amber Warning
51
⚠️Amber Warning · Needs priority action

Correct the removable shelf/opening above the automated crates on the network-hub side so it aligns with the right-side shoe-box/open-unit level.

Correct the wrong shelf and opening height in the gaming-room hub area.

15 Aug 2026Latest

The removable shelf/opening above the automated crates on the network / smart-home hub side is currently too low/small. It must be corrected to match the level and opening height of the corresponding right-side shoe-box/open unit above the seating area, so both sides are visually and functionally aligned. The shelf should not be aligned to the beam level. Adjust the removable shelf properly so the shoe crate currently kept on the side can fit inside this unit as intended. This remains pending.

Amber Warning
52
⚠️Amber Warning · Needs priority action

Fix the wire-manager cut-out in the gaming-room TV unit and fit both wire managers properly.

Correct the gaming-room TV wire-manager fit and finishing.

15 Aug 2026Latest

The square wire-manager cut-out in the gaming-room TV unit is too small, so the wire managers are not fitting correctly. Enlarge/correct the cut-out and fit both wire managers properly. The fit must be secure and precise — neither loose nor excessively tight. This remains pending.

Amber Warning
53
⚠️Amber Warning · Needs priority action

Bring out the pending light wire at the center of the gaming-room seating area.

Pull out and correctly route the pending gaming-room light wire.

15 Aug 2026Latest

The light wire at the center of the gaming-room seating area is still inside the unit and has not been brought out. The carpenter must make the required opening in the unit and pull the wire out for the light point. This is carpenter work; the electrician will not drill/cut into the carpentry unit. Complete this before electrical light installation. This remains pending.

Amber Warning
54
⚠️Amber Warning · Needs priority action

Fix the dummy above the open unit on the left side of the gaming-room seating area, towards the network-hub side.

Correct the improperly fixed dummy panel in the gaming-room seating/network-hub area.

15 Aug 2026Latest

The dummy above the open unit on the left side of the gaming-room seating area, towards the network / smart-home hub side, is not fixed correctly. Refit and secure the dummy properly so it is aligned, stable, and finished neatly with the surrounding unit. This remains pending.

Amber Warning
58
🚨Red Priority · Needs priority action

Fix the gaming-room hydraulic lift-up mechanism and push-to-open operation.

Rejected completion: TV lift is not opening correctly and desk-area lift mechanisms are too tight.

26 Jul 2026

The hydraulic lift-up mechanism and push-to-open function are not working smoothly or as expected. Both must be adjusted and fixed.

28 Jul 2026

Completed.

15 Aug 2026Latest

The previous completion status is not accepted based on the current site condition. The hydraulic lift above the TV is not opening with the push-to-open mechanism and must be fixed. The hydraulic lifts above the desk area are still very tight, and the push-to-open mechanism is struggling to operate. This task remains pending until all hydraulic lift-up shutters open and close smoothly with the push-to-open mechanism.

Red Priority
ROOM / AREA

Kitchen & Utility

17pending from interior team
61

Replace the existing wooden shutters in the hob area with fluted-glass shutters.

21 Jul 2026

Glass-shutter order will be placed only after the remaining kitchen work is completed. The current carpenter is frustrated, so this work will be completed by a new carpenter after the present carpenters move out. The interior team will take full responsibility for arranging and completing this work.

26 Jul 2026

Still pending and not yet completed.

28 Jul 2026

Additional work will be carried out after 2 Aug 2026. The order will be confirmed later.

15 Aug 2026Latest

The wooden shutters have still not been replaced with the fluted-glass shutters. The unit continues to have the existing wooden shutters as of today. Replacement with the finalized glass shutters remains pending.

Pending
62

Install the missing wooden shutter above the OTG / steam oven.

15 Aug 2026Latest

The wooden shutter above the OTG / steam oven is missing and has not yet been installed. This remains pending.

Pending
63
🚨Red Priority · Needs priority action

Fix the LPG unit: enlarge the internal gas-pipe cut-out, secure the loose ventilation grille, and correct the skirting alignment so it does not scrape the floor.

Safety and functionality: correct the LPG pipe opening, loose grille and floor-scraping skirting.

15 Aug 2026Latest

Inside the LPG unit, the gas-pipe cut-out is too small and must be enlarged to provide proper clearance. The ventilation grille/vent on the LPG-unit door is very loose, is coming out/falling off, and must be fixed securely. The skirting is dragging/scratching against the floor when the LPG-unit door is opened and closed; correct the door/skirting alignment so the skirting does not touch or scrape the floor during operation. This remains pending.

Red Priority
64
⚠️Amber Warning · Needs priority action

Replace the incorrect undersized plate accessory in the bottom drawer below the hob and align all three hob-unit drawers for smooth operation.

Replace the wrong-sized plate accessory and correct the kitchen drawer alignment.

15 Aug 2026Latest

In the hob unit, below the hob there are three drawers. The plate accessory provided in the bottom/last drawer is smaller than the tandem box, does not fit correctly, and is the wrong size. Replace it with the correct-size plate accessory that properly fits the tandem box. Also align and adjust all three drawers below the hob so they open and close smoothly without tightness, rubbing, or misalignment. This remains pending.

Amber Warning
65
⚠️Amber Warning · Needs priority action

Fix and correctly align/install the Magic Corner S pull-out so it operates smoothly and without excessive resistance.

Adjust the Magic Corner S so it operates smoothly without excessive force.

15 Aug 2026Latest

The Magic Corner S pull-out is very hard to operate and is not working smoothly as expected. The installation/alignment appears incorrect. Inspect, realign, adjust, and fix the mechanism so the pull-out opens and closes smoothly and can be used normally without excessive force. This remains pending.

Amber Warning
66
⚠️Amber Warning · Needs priority action

Fix and properly secure the bottle pull-out door so it is sturdy, aligned, and operates smoothly.

Correct the shaky, bending bottle pull-out and make its operation smooth.

15 Aug 2026Latest

The bottle pull-out door is not sturdy. It is very shaky and bends/flexes when pulled or closed, indicating that it is not fixed or aligned properly. It is also not operating smoothly as expected. Inspect the fixing, alignment, and mechanism; reinforce and adjust it so the door is stable, does not bend or wobble, and opens/closes smoothly. This remains pending.

Amber Warning
67

Complete the missing Aquaguard faucet cut-out through the wood below the granite.

15 Aug 2026Latest

The Aquaguard faucet hole has already been made through the granite, but the corresponding cut-out through the wood below has not yet been made. Complete the matching hole through the wood so the Aquaguard faucet can pass through and be installed properly. This remains pending.

Pending
68
🚨Red Priority · Needs priority action

Design, fabricate, and install the pending dustbin unit below the utility sink, only after dimensions/specifications are shown and approved.

Approve and build the utility dustbin unit without blocking drains, valves, pipelines or maintenance access.

15 Aug 2026Latest

The dustbin unit below the utility sink has not yet been started or fabricated and remains pending. Before fabrication/installation, share the proposed unit specifications, including height, width, depth, overall dimensions, box configuration, and installation layout. The design must account for all existing plumbing and service points. It must not cover or obstruct the drain/drain hole, any valves, the main valve, or any other existing installation below the sink. Keep all pipelines in mind, including pipelines running at the back and along the right side, and maintain proper clearance and access for operation, inspection, maintenance, and future servicing. The dustbin unit must be designed around these existing installations without hampering them. Proceed with fabrication and installation only after the complete design, dimensions, clearances, and plumbing accommodation are shown and approved by and Sharoon.

Red Priority
69
🚨Red Priority · Needs priority action

Complete the required carpenter cut-outs in the utility-area woodwork for the washing machine inlet/outlet and electrical point, and for the dryer electrical point.

Complete washing-machine inlet, outlet and electrical cut-outs plus the dryer electrical-point cut-out.

15 Aug 2026Latest

The required wood cut-outs near the washing machine and dryer are still pending and must be completed by the carpenter. Near the washing-machine inlet point, make the wood cut-outs required for the washing-machine inlet tap, outlet/drain arrangement, filter/plate fitting, and electrical point so the fittings and plate can be installed properly. Also make the dryer electrical-point cut-out in the wood of the upper unit above the dryer. The required openings should be approximately 3 inches wide; they may be square or circular as appropriate, but must provide proper clearance and a neat finished fit. These are carpenter cut-outs in the woodwork and remain pending.

Red Priority
70
🚨Red Priority · Needs priority action

Provide a removable 6 × 6 drain-access cut-out in the wooden base next to the washing machine unit.

Provide the required 6×6-inch removable drain-maintenance access opening.

15 Aug 2026Latest

A 6 × 6 inch access cut-out is required in the wooden base next to the washing machine unit to access the drain point below. The cut-out must have a removable closing/opening cover similar to the removable wire-manager-style access panel used below the gaming-room TV unit. Provide a small finger/access hole in the removable cover so it can be lifted out and put back easily whenever drain access is required. The panel should sit neatly and securely when closed while allowing quick future access to the drain. This carpenter work is still pending.

Red Priority
71

Install the missing push-to-open mechanism for the janitor unit in the utility area.

15 Aug 2026Latest

The push-to-open mechanism for the janitor unit in the utility area is missing and has not been installed. Install the required push-to-open hardware and adjust it so the janitor-unit shutter opens and closes smoothly and reliably. This remains pending.

Pending
77
🚨Red Priority · Needs priority action

Install the hydraulic lift-up shutters.

Fix unreliable push-to-open and closing of kitchen hydraulic shutters, or provide the approved black handle.

21 Jul 2026

Hydraulic fittings remain pending.

26 Jul 2026

Hydraulic lift-up shutters are installed.

15 Aug 2026Latest

The hydraulic lift-up shutters are installed, but the task is not complete because they are not working as expected. The shutters do not close properly, and the push-to-open mechanism is not opening them reliably. Fix and adjust the hydraulic lift and push-to-open mechanism so the shutters open and close smoothly. If this cannot be made reliable, provide and install a black profile handle, matching the lower unit, so the shutters can be opened and closed properly. This remains pending.

Red Priority
78
⚠️Amber Warning · Needs priority action

Complete the dishwasher door/panel with skirting and required cut-out.

Complete the dishwasher panel and skirting seamlessly without gaps or door interference.

21 Jul 2026

Complete skirting first, then panel fitting. Dishwasher inlet/outlet holes and electrical point are also pending.

26 Jul 2026

Dishwasher door-panel skirting is not yet completed. Waiting for dishwasher installation before finishing. Still pending.

28 Jul 2026

Panel is ready. It will be completed after dishwasher installation.

15 Aug 2026Latest

Dishwasher door/panel with skirting and dishwasher-door installation are still not completed. This task remains pending. Complete the panel and skirting with a seamless finish, ensuring there are no visible gaps on either side. The dishwasher door must open and close smoothly without obstruction, rubbing, misalignment, or any other issue.

Amber Warning
83

Replace/fix the left-side laminate inside the kitchen rolling-shutter unit to cover the mistakenly made holes.

15 Aug 2026Latest

Inside the kitchen rolling-shutter unit, the right-side laminate has already been fixed to cover the mistakenly made holes. The left-side holes are still visible and remain as-is. Replace/fix the laminate on the left side as well so the holes are fully hidden and the inside finish is neat and seamless. Right side completed; left side pending.

Pending
86
🚨Red Priority · Needs priority action

Confirm how the sharp edges on the kitchen glass-unit profile and handles will be covered, finished, or fixed to ensure a safe and premium finish.

Safety issue: properly finish every rough or sharp kitchen glass-unit edge.

21 Jul 2026

Sharp silver edges remain a quality and safety concern. Interior team must propose and complete a safe premium finish.

26 Jul 2026

Silver-edge trimmings remain visible. Still pending.

28 Jul 2026

Will be taken care of.

15 Aug 2026Latest

The glass-unit profile edges are still sharp and rough. This is not completed and remains pending. The interior team must rectify the sharp/rough edges and finish them safely and neatly.

Red Priority
88
⚠️Amber Warning · Needs priority action

Install the pending mesh drawer in the kitchen.

Install the kitchen mesh drawer that is already available on site.

21 Jul 2026

Tandem drawers are ready, but the pending mesh drawer/shelf still needs installation.

26 Jul 2026

Dryer is fixed, but the mesh is not yet installed. Still pending.

28 Jul 2026

Under production.

15 Aug 2026Latest

The mesh has arrived at the site, but installation is still pending and has not yet been completed. The task remains pending until the mesh drawer is fully installed.

Amber Warning
89
⚠️Amber Warning · Needs priority action

Provide the internal partition inside the kitchen mesh tandem box with the mesh door, for separate storage of onions, potatoes, and similar items, as discussed earlier.

Complete the onion-and-potato internal partition inside the kitchen mesh unit.

21 Jul 2026

Internal mesh partition for separate onion/potato storage is still pending.

26 Jul 2026

Still pending.

28 Jul 2026

Will be completed on Friday or Saturday.

15 Aug 2026Latest

The promised internal partition inside the kitchen mesh tandem box is still not completed. This remains pending as of today.

Amber Warning
ROOM / AREA

Living Area

1pending from interior team
92
⚠️Amber Warning · Needs priority action

Fix the laminate joint finishing at the curved transition between the living and dining areas near the TV unit.

Seamlessly rework gum, overlap and protruding laminate at the living/dining curved joint.

15 Aug 2026Latest

At the curved transition between the living and dining areas near the TV unit, two laminate sheets meet and the joint finishing is not proper. The laminates are slightly overlapping in some places, adhesive/gum is still visible, and portions of the joint are protruding instead of sitting flush. Rework and finish the laminate joint properly so both sheets align cleanly and seamlessly along the curve, with no overlap, visible gum, protruding edges, unevenness, or rough finishing. This finishing work remains pending.

Amber Warning
ROOM / AREA

General / Entire House

5pending from interior team
94
🚨Red Priority · Needs priority action

Complete full deep cleaning of the house and remove all dirt, dust, wooden powder, gum/Fevicol marks, stains, and debris created during the interior work.

Complete full-house deep cleaning to avoid the recorded ₹6,000 direct deduction.

21 Jul 2026

Full deep cleaning is not included in the interior contract and will be separately chargeable to . Basic carpentry dust/debris cleanup, gum removal, and surface dusting are included.

26 Jul 2026

Still pending. The site remains dirty and must be cleaned to the condition provided before work started.

28 Jul 2026

Not part of our quotation. Basic cleaning will be done if required. Deep cleaning can be provided at an additional cost.

15 Aug 2026Latest

The interior team is refusing to clean the house, even though had handed over the complete house to them in top-notch clean condition before the interior work. As of today, practically no cleaning has been done. The floors and walls remain dirty, with gum/Fevicol marks, wooden powder, dust, and work-related dirt visible throughout the house. Since the interior work has dirtied the property and the interior team is expected to hand over the project in a properly cleaned condition, ₹6,000 will be deducted directly from the pending payment if they do not complete the required cleaning. This deduction is final and non-negotiable. The task remains pending.

Red Priority
95
🚨Red Priority · Needs priority action

Clear all debris from the balcony and parking area.

Clear balcony and parking debris to avoid the recorded ₹3,000 direct deduction.

21 Jul 2026

Balcony debris and parking-area materials must be cleared.

26 Jul 2026

All debris and materials in the utility area remain as-is and have not yet been moved down.

28 Jul 2026

Completed.

15 Aug 2026Latest

The 28 Jul 2026 completion update is not accepted based on the current site condition. There is significant debris still present in both the parking area and the balcony. The parking area contains woodwork items/waste, plumbing items/waste, and bathroom-related materials/waste. The balcony also contains substantial debris and waste from the interior work. No client-side work or painting work has been carried out that would account for this debris; the current waste is from the interior/woodwork/plumbing/bathroom work and must be cleared by the interior team. This task remains pending. If the balcony and parking-area debris are not fully cleared by the interior team, ₹3,000 will be deducted from the pending payment towards the cost of cleaning and debris removal.

Red Priority
96
⚠️Amber Warning · Needs priority action

Send all pending payment receipts to Rohit for payments already completed.

Send all outstanding receipts for already-paid sink, marble-sink and plumbing-related payments.

21 Jul 2026

Consolidated record needed: approximately ₹5 lakh paid by bank and approximately ₹5 lakh paid in cash. Cash receipts are missing; contractor to reshare exact amounts and receipts.

26 Jul 2026

Bathroom-renovation payment receipts are still pending and have not yet been received.

28 Jul 2026

OK.

15 Aug 2026Latest

Bathroom-renovation receipts that were already shared in the WhatsApp group do not need to be resent. The pending requirement is only for receipts that have not yet been shared for payments that have already been made. Recent payment receipts are still pending, including receipts for the sink, utility sink, marble sink, and other plumbing-related payments already completed. Please send all outstanding receipts for completed payments that have not yet been shared. Ignore any receipts that have already been provided in the WhatsApp group. This item remains pending until all missing payment receipts are shared with .

Amber Warning
100
🚨Red Priority · Needs priority action

Clean all balconies and the utility area, and rectify all visible spit marks.

Remove all spit, tobacco and pan-masala stains to avoid the recorded ₹1,000 direct deduction.

26 Jul 2026

The balconies and utility area are very dirty and require complete cleaning. Spit marks are visible throughout the balconies and utility area and must be properly cleaned and removed.

28 Jul 2026

OK.

15 Aug 2026Latest

This item is still pending. The marks referred to here are spit marks. Workers have spat tobacco/pan masala or similar material in the balconies and utility area. These spit stains/marks must be completely cleaned and removed by the interior team, along with proper cleaning of the affected balcony and utility surfaces. Keep this item unchecked until all visible spit marks are fully cleaned. If this cleaning is not completed, ₹1,000 will be deducted directly from the pending amount towards cleaning/removal of these spit marks.

Red Priority
101
⚠️Amber Warning · Needs priority action

Install all selected handles and knobs throughout the house and provide the pending quotation.

Complete correct delivery and installation of every paid knob, handle and tower bolt throughout the house.

26 Jul 2026

Handles and knobs selected for doors, drawers, bathroom units, and other applicable locations are still pending installation. The quotation for these handles and knobs has also not yet been provided. Both quotation and installation remain pending.

28 Jul 2026

Order confirmed.

15 Aug 2026Latest

Full payment has been made and the order was placed. Knobs, handles, and tower bolts have reached the site only partially. Several selected items are still missing, and some of the items delivered are incorrect/wrong and do not match the finalized selection. The tower bolt has reached the site but has not yet been installed. Only a few knobs/handles have been installed so far; installation remains pending in most locations. It is the interior team's responsibility to follow up with the store/vendor, arrange delivery of all remaining correct selected knobs, handles, and tower bolts, replace any incorrect items, and install each item in the designated location as finalized. This task remains pending until all correct items are delivered and fully installed throughout the house.

Amber Warning